How would you integrate the "quick wins" into the delivery process?
Anonymous
Review them with the client, prioritise them for user/business value, and then package them as a separate SOW to decouple the project risk from the main work stream. Then either schedule to complete them first or assign another team to work on them in parallel on the timeline, considering dependencies on deliverables.